Do not worry about that if you are stuck in the 310-400 exam difficulties, CertBus will assist you all your way through the 310-400 Sun Certified Integrator for Identity Manager 7.1 exam with the most update 310-400 PDF and VCE dumps. CertBus exam 310-400 preparation materials are the most comprehensive material, covering every key knowledge of 310-400 Sun Certified Integrator for Identity Manager 7.1 exam.

We CertBus has our own expert team. They selected and published the latest 310-400 preparation materials from SUN Official Exam-Center: http://www.certgod.com/310-400.html

QUESTION NO:20

An application uses a large XML document that contains information about 10,000 customers.

The application is performing poorly, with slow responses to requests for customers with a

particular hobby. Which combination of the following could an XML developer use to facilitate

logic for alleviating the problem?

A. Create XML documents for each of the hobbies.

B. Store IDs in a

QUESTION NO:159

A hybrid mobile application named App1 is failing to connect to the Worklight Server with the following

error code: “Application Error – The connection to the server was unsuccessful” Knowing that the

application should be available at “http://srv.ent.com:9099/wl” but without any access to the Worklight

Console, how can the support engineer ensure that the application App1 has been properly deployed?

A. Query the is-alive URL at “http://srv.ent.com:9099/wl/ws/rest/vitality?app=App1”

B. Query the preview URL at “http://srv.ent.com:9099/wl/apps/services/preview/App1/App1.html”

C. Invoke the Worklight Server Mobile Browser Simulator

at”http://srv.ent.com:9099/wl/_MobileBrowserSimulator/index.html?app=App1″

D. Use a remote debugging tool such as Weinre or iWebInspector to inspect the request to the

application\’s init resource at”http://srv.ent.com:9099/wl/apps/services/api/App1/common/init”

ExamReal.com — 100% Real QandAs | 100% Real Pass

Correct Answer: A

QUESTION NO: 41

A customer has the following equipment installed in their data center:

–an IBM BladeCenter H chassis

–two power supplies

–six LS21 blades

–twoNortel L27 GESMs

The customer purchased a new LS22 7901 blade server and a BladeCenter Storage and I/O (SIO)

Expansion blade with two 146GB SAS drives. The customer is now unable to load a supported

network operating system to the LS22. Which of the following must be done so the operating

system can be successfully loaded?

A. add two additional power supplies

B. update the BIOS and firmware of the LS22

C. use theServeRAID Manager to create the RAID array

D. use theServerGuide CD to install the operating system

Answer: A

QUESTION NO:33

A customer has a mission-critical application with redundant fabrics. The customer plans to replace older

EMC Symmetrix 8830 systems with an IBM System Storage DS8700 and an IBM SAN Volume Controller

(SVC). Which statement best describes the way to minimize the impact of data migration on the production

environment?

A. the production environment does not require an outage

B. the production environment requires an outage to install the SVC

C. the production environment requires an outage to install the DS8700

D. the production environment requires an outage to remove the EMC systems

Correct Answer: B

QUESTION NO:19

A customer has one mainframe and ten open system servers in their current environment. They plan to

add the servers to an IBM DS8700 system with four array sites. How many extent pools should be created

to provide the best resource utilization of the DS8700?

A. 1

B. 2

C. 4

D. 6

Correct Answer: C