Don’t worry about how to get yourself well prepared your SAP Application Associate C_TSCM42_65 exam! CertBus will work you out of your SAP Application Associate C_TSCM42_65 exam with the latest updated C_TSCM42_65 SAP Certified Application Associate – Production – Planning and Manufacturing with SAP ERP 6.0 EHP5 PDF and VCE dumps. CertBus provides the latest real SAP SAP Application Associate C_TSCM42_65 exam preparation material, covering every aspect of C_TSCM42_65 exam curriculum.

We CertBus has our own expert team. They selected and published the latest C_TSCM42_65 preparation materials from SAP Official Exam-Center: http://www.certgod.com/C_TSCM42_65.html

QUESTION NO:9

What sequence do you follow in master data maintenance to define the production of a material?

A. Create BOM -> Create work centers -> Create routing -> Carry out component assignment in

BOM or routing

4

B. Create BOM -> Create work centers -> Create routing -> Carry out component assignment in

work center

C. Create routing -> Create work centers -> Create BOM -> Carry out component assignment in

BOM or routing

D. Create work centers -> Create routing -> Create BOM -> Carry out component assignment in

work center

Answer: A


QUESTION NO:19

Which objects can affect the calculation of capacity requirements for an operation? (Choose three)

A. Standard values (routing)

B. Transport time (routing)

C. Operation control key (routing)

D. Formulas (work center)

E. In-house production time (material master)

Answer: A,C,D


QUESTION NO:15

In which master data object do you set the standard values for an operation?

A. Work Center

B. Production Resource/Tool (PRT)

C. Material Master

D. Routing

Answer: D


QUESTION NO:17

Which activity can trigger an automatic availability check for the components of a production

order?

A. Goods receipt for a missing part

B. Material staging

C. Order release

D. Order rescheduling

Answer: C


QUESTION NO:14

What could be a consequence of the confirmation of an operation?

A. Settlement of the actual costs

B. Reduction of capacity requirements

C. Rescheduling of the production order

D. Update of the planned costs

Answer: B


QUESTION NO:12

For which of the following objects can you enter a confirmation? (Choose two)

A. Production order

B. Production order operation

C. Trigger Point

D. Work Center

Answer: A,B


QUESTION NO:11

In SAP ECC, you calculate the standard available capacity for a work center capacity using the

following data:

– Start: 7:00:00 a.m.

– End: 3:00:00 p.m.

5

– Break duration: 1 hour

– Rate of utilization: 80%

– Overload: 110%

– Number of individual capacities: 1

How large is the standard available capacity?

A. 7 hours

B. 6.16 hours

C. 5.6 hours

D. 8 hours

Answer: C


QUESTION NO:1

What features related to process orders can be used to fulfill Good Manufacturing Practices

(GMP) requirements? (Choose three)

A. Availability check

B. Digital signature

C. Resource selection

D. Electronic batch record

E. Approved master recipes

Answer: B,D,E


QUESTION NO:5

What does SAP ERP mean?

A. SAP ERP is a planning system in which extended planning processes can be mapped.

B. SAP ERP is a system hardware that includes modules for purchasing, sales and distribution,

materials management, production and so on.

C. SAP ERP is a technological platform, on the basis of which customer-specific extensions can

be imported.

D. SAP ERP is an application that an enterprise can use to manage its business processes

efficiently.

Answer: D


QUESTION NO:7

What is a feature of the simu-lation mode for material requirements planning in SAP ECC?

A. It posts planning results to the database automatically.

B. It propagates exception messages from a component to the finished product.

C. It calculates the delay time which may occur in planning.

D. It triggers multilevel bottom-up scheduling.

Answer: C


CertBus exam braindumps are pass guaranteed. We guarantee your pass for the C_TSCM42_65 exam successfully with our SAP materials. CertBus SAP Certified Application Associate – Production – Planning and Manufacturing with SAP ERP 6.0 EHP5 exam PDF and VCE are the latest and most accurate. We have the best SAP in our team to make sure CertBus SAP Certified Application Associate – Production – Planning and Manufacturing with SAP ERP 6.0 EHP5 exam questions and answers are the most valid. CertBus exam SAP Certified Application Associate – Production – Planning and Manufacturing with SAP ERP 6.0 EHP5 exam dumps will help you to be the SAP specialist, clear your C_TSCM42_65 exam and get the final success.

C_TSCM42_65 Latest questions and answers on Google Drive(100% Free Download): https://drive.google.com/file/d/0B_3QX8HGRR1mTDllMEw3S3dTYk0/view?usp=sharing

C_TSCM42_65 SAP exam dumps (100% Pass Guaranteed) from CertBus: http://www.certgod.com/C_TSCM42_65.html [100% Exam Pass Guaranteed]

Why select/choose CertBus?

Millions of interested professionals can touch the destination of success in exams by certgod.com. products which would be available, affordable, updated and of really best quality to overcome the difficulties of any course outlines. Questions and Answers material is updated in highly outclass manner on regular basis and material is released periodically and is available in testing centers with whom we are maintaining our relationship to get latest material.

BrandCertbusTestkingPass4sureActualtestsOthers
Price$45.99$124.99$125.99$189$69.99-99.99
Up-to-Date Dumps
Free 365 Days Update
Real Questions
Printable PDF
Test Engine
One Time Purchase
Instant Download
Unlimited Install
100% Pass Guarantee
100% Money Back
Secure Payment
Privacy Protection