QUESTION NO:51

A “previous release to current release” system migration is being performed. An application on the source system manages image files stored in the IFS, viewed using PCs.

The Go Save menu, option 21 (full system save), was used to create the backup tape used in the migration process.

After the data is migrated and the new system set up, none of the images are available.

Which situation on the source system IFS directory, at the time of the backup, is the most likely cause of the problem?

A. The “Hidden file” attribute was set to “Yes”

B. The “Can be saved” attribute was set to “No”.

C. The “Need to archive (PC)” attribute was set to “Yes”.

D. The “Need to archive (System)” attribute was set to “No”.

Correct Answer: B

QUESTION NO: 33

A solution implementer needs to generate an X.509 private key and provide an associated

Certificate Signing Request (CSR) to a certificate authority for signing and issuing of an associated

public certificate. The private key, certificate signing request, and public certificate files must be

archived in a certificate management system external to the appliance.

Which one of the following requests to the XML Management Interface will the solution

implementer use to satisfy this requirement?

A. Option A

B. Option B

C. Option C

D. Option D

Answer: C

Explanation:

QUESTION NO:48

A storage specialist needs to create a new host connection using the DSCLI. Which of the following

parameters identifies the host?

A. hosttype

B. volume group

C.

ioports

D. WWPN

Correct Answer: D

QUESTION NO:28

An administrator needs to upgrade their Flexible Service Processor\’s (FSP) firmware for an HMC managed Power 720. They are currently running AL730_085. The latest corrective service on Fix Central is AL730_1 12_092.

Which statement is correct regarding the installation of this corrective service package?

A. Since this is an HMC managed FSP, the installation of the corrective service will be concurrent.

B. Since the FSP will remain at the same 730 code stream level the installation of the corrective service will be concurrent.

C. Since the 092 is greater than the currently running 085 fix pack level, the installation of the corrective service will be disruptive.

D. Since the 112 is greater than the currently running 085 fix pack level, the installation of the corrective service will be disruptive.

Correct Answer: C

QUESTION NO:157

A developer previewing a Worklight application for an Android device in the Mobile Browser Simulator now

wants to preview the application for an iOS device. Is it possible to preview the application for both devices

on a same page of the Mobile Browser Simulator?

A. No because the developer can view only one device at a time.

B. Yes by clicking the Add Device button to select another device.

C. Yes by enabling the User Agent switching to select another device.

D.

Yes by adding another device in the Device section of the Cordova API plugin.

Correct Answer: B