How to pass 000-434 exam easily with less time? CertBus provides the most valid 000-434 exam preparation material to boost your success rate in IBM 000-434 IBM Tivoli Netcool Performance Manager for Wireless V9.1.2 exam. If you are one of the successful candidates with CertBus 000-434 PDF and VCEs, do not hesitate to share your reviews on our IBM materials.
We CertBus has our own expert team. They selected and published the latest 000-434 preparation materials from IBM Official Exam-Center: http://www.certgod.com/000-434.html
QUESTION NO: 61
A retailer recently upgraded their IBM Sterling Order Management from an older version to 9.1.
While verifying the installation after the upgrade was completed, the resource manager found that
the APIs were not returning data from the extended columns of product tables. The release
manager believes the root cause to be a defective build process. Which aspect of the build
process was defective?
A. The build process was not using the correct version of the JVM to compile the custom classes.
B. There is nothing wrong with the build process. Data from extended columns will not be carried
over as part of an upgrade.
C. In order to view data from extended columns, custom classes following the “data access object”
pattern have to be written and compiled as part of the build process.
D. The database extension xml was not present in the correct folder and hence the build process
was not including it and did not detect any of the database extensions.
Answer: D
Explanation:
QUESTION NO:18
Refer to the exhibit to answer the question.
The Web site for a financial services company will include both web-based trading (e-trades) and
the financial research reports to help investors make their decisions. As part of the application
architecture, note the following:
* As the data interchange format between the web-based application and the company
QUESTION NO:55
Companycom is considering a partitioned solution with one of the LPARs utilizing 12 CPUs.
Multiple applications will be loaded on this large LPAR. However, the customer wants to ensure
some tasks will have higher priority access to the CPU and memory resources. Which of the
following solutions would best satisfy the requirement?
A. Loadleveler
B. AIX Workload Manager
C. Partition Load Manager
D. Tivoli Provisioning Manager
Answer: B
QUESTION NO:145
How does Worklight handle globalization of application messages?
A. It uses a user-provided JavaScript file.
B. It uses language-specific XML resources.
C.
It uses a system-provided globalization file.
D.
It uses a native language translation library.
Correct Answer: A
QUESTION NO: 61
The parallel framework was extended for real-time applications. Identify two of these aspects.
(Choose two.)
A. XML stage.
B. End-of-wave.
C. Real-time stage types that re-run jobs.
D. Real-time stage types that keep jobs always up and running.
E. Support for transactions within source database connector stages.
Answer: B,D
Explanation: