Tens of thousands of competitors, pages of hard questions and unsatisfied exam preparation situations… Do not worried about all those annoying things! We, CertBus, help you with your IBM 000-633 Rational object oriented analysis and design-part1 exam. CertBus will assist you clear the 000-633 exam with 000-633 PDF and VCE questions. CertBus exam dumps are the most comprehensive ones.

We CertBus has our own expert team. They selected and published the latest 000-633 preparation materials from IBM Official Exam-Center: http://www.certgod.com/000-633.html

QUESTION NO:116

A storage specialist wants to create a fixed-block volume in the extent pool P10, in rank group 0. Which of

these volumes cannot be created?

A. 2001

B. 2B00

C. 3A01

D. 5E00

Correct Answer: B

QUESTION NO:161

A developer is using a Worklight Studio installation that is configured with the Android 2.2 SDK and the

corresponding Google USB driver. The developer has connected an Android device to the machine via a

USB cable. The developer tries to run the application on the device but does not see the device listed as a

target. What can be a cause for this issue?

A. Worklight does not support testing on Android 2.2 devices.

B. Installed Google USB driver is deprecated and must be explicitly enabled.

C. Installed Google USB driver does not support the device connected to the machine.

D.

The worklight.properties file of the application is not configured to allow USB connection.

Correct Answer: C

QUESTION NO:75

A customer has multiple applications on multiple open platforms in their current environment based on IBM

System Storage DS8100. They plan to set up a business continuity solution that meets the objective of

zero or little data loss for their business critical data. The customer has indicated that cost is a factor.

What should the storage specialist recommend?

A.

a DS8700 in the Business Continuity site with a Metro Mirror license

B.

a DS8700 with SAN Volume Controller in the Business Continuity site

C. a DS8700 in the Business Continuity site with Global Copy license

D. two new DS5300 servers (production and Business Continuity site) with a Global Copy license

Correct Answer: A

QUESTION NO:76

A customer has two data centers, 500 kilometers apart. The customer requests a proposal for new

storage subsystems and a disaster recovery solution that provides consistent data in the event of a

disaster at the local site. Which IBM System Storage DS8000 solution should the storage specialist

propose to the client?

A. Metro/Global Mirror

B. Metro Mirror

C. Global Copy

ExamReal.com — 100% Real QandAs | 100% Real Pass

D. Global Mirror

Correct Answer: D

QUESTION NO: 40

An IBM System x Technical Expert has a prospective customer who is very excited about X5 and

they are working on configurations. During the process the customer has changed the design

numerous times and has significantly increased the scope. They recently selected a Business

Partner who has been involved in the last few design changes. What steps should be taken to

make sure the customer is satisfied with the solution?

A. Turn over current design toTechline to create configurations

B. Perform knowledge transfer of design requirements to Business Partner then disengage

C. Work with business partner to engageTechline to assist with configurations and request

Technical and Delivery Assessment (TDA)

D. Work with business partner to engageTechline to create configurations

Answer: C